Scituate New Senior Center / Recreation Center Renovation Project Update #2
Update #2
Posted on: January 31, 2020 - 11:40am
Progress update and upcoming three-week look-ahead schedule
The project has been divided into main work areas as follows:
General/Site Conditions
- The General Contractor has mobilized to the site.
- Temporary Phase 1 construction fence and partial green fabric fence screening has been installed.
- Columbia Gas has relocated the gas service piping to the former Gates School.
- Vegetation at the fence along west side to be trimmed to install green fabric fence screening.
- Additional site prep and erosion control to be performed.
- Field office trailers have been delivered and will be provided with power.
Senior Center
- C-Wing non-asbestos demolition has started.
- Preparation for and abatement of the C Wing abatement has started.
- C Wing abatement to continue for the next 2 to 3 weeks.
- Pre-demolition cutting and capping of utilities from B Wing has started.
- Solid partition to be installed at B/C Wing connection.
Recreation Center
- No work has started except temporary construction fence on south side.
Please note: the above schedule is based on information provided by the General Contractor during the weekly job meetings, and is subject to change depending on weather, unforeseen conditions, or other reasons.