Scituate New Senior Center / Recreation Center Renovation Project – Update #5
Posted on: February 21, 2020 - 9:51am
Progress update and upcoming three-week look-ahead schedule
The project has been divided into main work areas as follows:
General/Site Conditions
- Erosion control completed and inspected
- Tree protection ongoing
- Truck wash bay for demolition completed
- Start utilities
Senior Center
- C Wing building demolition to start on 2/24 for 2 weeks
- Start building excavation
Recreation Center
- Prep for new stairs and ramp ongoing
Please note: the above schedule is based on information provided by the General Contractor during the weekly job meetings, and is subject to change depending on weather, unforeseen conditions, or other reasons.