Scituate New Senior Center / Recreation Center Renovation Project Update #3
Update #3
Progress update and upcoming three-week look-ahead schedule
The project has been divided into main work areas as follows:
General/Site Conditions
- Vegetation at the fence along west side to be trimmed to install green fabric fence screening.
- Additional site prep and erosion control to be performed.
Senior Center
- C Wing abatement to continue for the next week.
- C Wing clearance testing.
- C Wing building demolition.
Recreation Center
- Demolition of concrete entry stairs on south (tennis) side. Prep for new stairs and ramp.
Please note: the above schedule is based on information provided by the General Contractor during the weekly job meetings, and is subject to change depending on weather, unforeseen conditions, or other reasons.