Scituate New Senior Center / Recreation Center Renovation Project Update #3

Update #3

Progress update and upcoming three-week look-ahead schedule

The project has been divided into main work areas as follows:

General/Site Conditions

  • Vegetation at the fence along west side to be trimmed to install green fabric fence screening.
  • Additional site prep and erosion control to be performed.

Senior Center

  • C Wing abatement to continue for the next week.
  • C Wing clearance testing.
  • C Wing building demolition.

Recreation Center

  • Demolition of concrete entry stairs on south (tennis) side. Prep for new stairs and ramp.

Please note: the above schedule is based on information provided by the General Contractor during the weekly job meetings, and is subject to change depending on weather, unforeseen conditions, or other reasons.