Scituate New Senior Center / Recreation Center Renovation Project – Update #4
Update #4
Posted on: February 19, 2020 - 10:24am
Progress update and upcoming three-week look-ahead schedule
The project has been divided into main work areas as follows:
General/Site Conditions
- Erosion control to be completed
- Tree protection ongoing
- Truck wash setup for demolition
Senior Center
- C Wing abatement of interior and windows complete
- C Wing building demolition to start week of 2/17
Recreation Center
- Demolition of concrete entry stairs on south (tennis) side complete
- Prep for new stairs and ramp ongoing
Please note: the above schedule is based on information provided by the General Contractor during the weekly job meetings, and is subject to change depending on weather, unforeseen conditions, or other reasons.