Scituate New Senior Center / Recreation Center Renovation Project Update #2

Update #2

Progress update and upcoming three-week look-ahead schedule

The project has been divided into main work areas as follows:

General/Site Conditions

  • The General Contractor has mobilized to the site.
  • Temporary Phase 1 construction fence and partial green fabric fence screening has been installed.
  • Columbia Gas has relocated the gas service piping to the former Gates School.
  • Vegetation at the fence along west side to be trimmed to install green fabric fence screening.
  • Additional site prep and erosion control to be performed.
  • Field office trailers have been delivered and will be provided with power.

Senior Center

  • C-Wing non-asbestos demolition has started.
  • Preparation for and abatement of the C Wing abatement has started.
  • C Wing abatement to continue for the next 2 to 3 weeks.
  • Pre-demolition cutting and capping of utilities from B Wing has started.
  • Solid partition to be installed at B/C Wing connection.

Recreation Center

  • No work has started except temporary construction fence on south side.

Please note: the above schedule is based on information provided by the General Contractor during the weekly job meetings, and is subject to change depending on weather, unforeseen conditions, or other reasons.