Roadwork Update

Milling and Paving

Milling and Paving of many streets impacted last year with water main replacement in the Town of Scituate will begin on Monday, April 9, 2018. Work hours will be from 7:00 am to 5:00 pm daily weather permitting. The roadways will be milled and castings adjusted the following few days before finish pavement is placed. Motorists should use caution for raised castings and seek alternate routes during construction hours.

The schedule is as follows:

April 9, 2018

  •             Country Way (North Scituate from Gannett Rd to Cohasset Town Line)
  •             Mordecai Lincoln Road (North Section near Former Hunters Pond Dam)

April 10, 2018

  •             Old Gannett Road
  •             Trenches on Gannett Road near Indian Trail

April 11, 12, 13, 2018 Minot Area

  •             Damon Lane
  •             Buttonwood Lane
  •             Grasshopper Lane
  •             Cherry Street
  •             Baileys Causeway (From Buttonwood Ln to Hatherly Rd)
  •             Hatherly Road (West of Gannett Rd)

April 16, 17, 18, 2018

  •             Hood Road
  •             Mann Hill Road
  •             Tilden Road (From Intersection of Ann Vinal Rd east toward Egypt Beach Road)
  •             Captain Peirce Road (From Intersection of Ann Vinal Rd south to RR Tracks)

April 19, 20, 2018

  •             Alden Road
  •             Egypt Avenue           
  •             Borden Road
  •             Morton Road
  •             Dayton Road
  •             First Avenue
  •             Second Avenue
  •             Third Avenue

April 23, 24, 25, 2018

  •             Kenneth Road
  •             Park Avenue
  •             Maple Avenue
  •             Wellesley Road
  •             Barker Road
  •             Bay Ridge Road

April 26, 27, 2018

  •             Tichnor Court
  •             Common Street

April 30, May 1, 2018

  •             Cornet Stetson Road (Rt 123)
  •             Country Way (East of the Rotary)

May 2, 2018

  •             Grove Street (Trenches)

The above schedule may change due to weather or other unforeseen conditions.

Motorists should seek alternate routes and residents in the work zone could experience short delays and should plan accordingly. Local traffic will be allowed in the work zones during the construction hours of 7:00 am and 5:00 pm. Thank you for your patience.